Question: Consider the AON graph of a project shown below. A 1 to A 2 . A 2 splits to A 3 and A 5 .

Consider the AON graph of a project shown below.
A1 to A2. A2 splits to A3 and A5. The path from A3 is A3, A4 A8 and A3, A6, A7, A8. The path from A5 is A5, A7, A8.
Which of the following statements is correct?
multiple choice
A1 is a predecessor activity to A2.
A2 is a successor activity of A1.
A3 and A5 can be carried out in parallel.
All of these statements are correct.