Question: Consider the AON graph of a project shown below. A4 A3 Figure 19.18 A6 Ag A7 A2 A1 A5 The activity times are 2, 5,

 Consider the AON graph of a project shown below. A4 A3

Consider the AON graph of a project shown below. A4 A3 Figure 19.18 A6 Ag A7 A2 A1 A5 The activity times are 2, 5, 1, 8, 5, 1, 3, and 3 days for activities Aj through Ag, respectively. What is the earliest completion time of the project? days Project time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!