Question: Consider the AON graph of a project shown below. A4 A3 Figure 19.18 A6 Ag A7 A2 A1 A5 The activity times are 2, 5,

Consider the AON graph of a project shown below. A4 A3 Figure 19.18 A6 Ag A7 A2 A1 A5 The activity times are 2, 5, 1, 8, 5, 1, 3, and 3 days for activities Aj through Ag, respectively. What is the earliest completion time of the project? days Project time