Question: Consider the assembly line balancing problem described in the table below: table [ [ Task , table [ [ Task Time ] ,
Consider the assembly line balancing problem described in the table below:
tableTasktableTask TimemintableImmediatePredecessors
a Develop a network for this assembly operation.
b Using the ranked positional weight technique, determine the resulting balance using a cycle time of minutes.
c Determine the number of work stations needed and the total idle times from part b