Question: Consider the Baseline Project budget for the camera prototype project shown below (Figure 13.8). (Note this data will be used for multiple questions) Assume that

Consider the Baseline Project budget for the camera prototype project shown below (Figure 13.8). (Note this data will be used for multiple questions)

Assume that at the end of period 1 the Actual Cost of Work Completed (AC) for Task A is 11 and the work is 60% complete. What is the Earned Value (EV) for Task A?