Question: Consider the batch process known as hot isostatic pressing (HIP). This operation is basically an oven where we put a number of parts in and
Consider the batch process known as hot isostatic pressing (HIP). This operation is basically an oven where we put a number of parts in and apply heat and pressure for a period of time. This particular operation takes 4 hours to process the batch with a standard deviation of 1.2 hours. The maximum number of parts the HIP can hold is 50 and parts arrive individually to the area at a rate of 10 parts per hour. The arrival process is considered to be Poisson in nature.
a) (5 points) Using the maximum batch size what would be the average time to form the batch (in hours)?
b) (11 points) Using the maximum batch size what would be the average cycle time through the operation (in hours) if we exclude the time to form the batch that we found in a?
c)((5 points) What is the minimum batch size for stability?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts