Question: Consider the below Gerit Chert sf a project x O inatla The number of workers needed for the actrinties are as below table [
Consider the below Gerit Chert sf a project
inatla
The number of workers needed for the actrinties are as below
tableActivityABCDWorkers
Develop a resource logding table, indicating number of workers needed during all weeks of the project life. What is the peak requirement of workers?