Question: Consider the below project information for questions 1-4. Activity Duration (days) Immediate Predecessor A 2 B --- 5 A 12 D A E B, C

Consider the below project information for

Consider the below project information for questions 1-4. Activity Duration (days) Immediate Predecessor A 2 B --- 5 A 12 D A E B, C 11 F B, C G E H D, F 10 I G, H 1. (25 pts.) Calculate the slack times of the activities. 2. (25 pts.) Calculate the total usable slack time without delaying the total project duration