Question: Consider the data for a simple project at Carlos Lopez's real estate development company, as given in the following table. a ) The expected completion

Consider the data for a simple project at Carlos Lopez's real estate development company, as given in the following table.
a) The expected completion time of the project is 34.8 days (enter your response rounded to one decimal place).
b) Referring to the standard normal table, the probability of the project being completed within 38 days is %(enter your response rounded to one decimal place).