Question: consider the differences among the three types of network schedule. Which network schedule uses three time estimates, and which network schedule uses only one time
consider the differences among the three types of network schedule. Which network schedule uses three time estimates, and which network schedule uses only one time estimate? A) Program Evaluation and Review Technique (PERT), Precedence Diagramming Method(PDM), B) Program Evaluation and Review Technique (PERT), Arrow Diagram Method (ADM), C) Precedence Diagramming Method (PDM), Arrow Diagram Method (ADM), D) Arrow diagram Method (ADM), Program Evaluation and Review Technique (PERT)