Question: Consider the following 7 activities: I know how to do the first part of the question, but how do you figure out b? how do
Consider the following 7 activities:

I know how to do the first part of the question, but how do you figure out b? how do you know to look-up z=1.28?
5. Consider a project having the following seven activities: Activity Immediate Predecessors Optimistic Time (weeks) 2 4 Most Likely Time (weeks) 3 4 A Pessimistic Time(weeks) 4 8 7 B 3 5 D 5 A A B B, C D E, F E 5 3 4 3 5 7 9 7 6 5 3 F G a) Using a forward and backward pass through the network, determine the expected completion time for the project and the critical path. b) What is the expected completion time required to have a 90% chance of finishing the project in 23 weeks? aStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock