Question: Consider the following activity network we discussed in class. It is known that the project needs 24 hours to complete. Which of the following cases
Consider the following activity network we discussed in class. It is known that the project needs 24 hours to complete. Which of the following cases would not increase the project duration? The activity time of A increases by 1 hour The activity time of B increases by 2 hours The activity time of B increases by 3 hours The activity time of B increases by 4 hours