Question: Consider the following: Activity Normal time Predecessor A 4 --- B 2 --- C 3 --- D 1 A E 4 B F 6 C
Consider the following:
| Activity | Normal time | Predecessor |
| A | 4 | --- |
| B | 2 | --- |
| C | 3 | --- |
| D | 1 | A |
| E | 4 | B |
| F | 6 | C |
| G | 2 | D,E |
If the duration of activity F is reduced by 1 days, the duration of the project can be reduced by _____ days. (Fill a number in the blank.)
Your Answer:
The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the crash time of all activities are zero:
| Activity | Duration (days) | Immediate predecessor | Crash cost per period |
| A | 2 | - | $100 |
| B | 3 | - | $150 |
| C | 11 | - | $200 |
| D | 5 | A | $30 |
| E | 7 | B | $400 |
What is the cost for crashing the project by 1 day?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts