Question: Consider the following: Activity Normal time Predecessor A 4 --- B 2 --- C 3 --- D 1 A E 4 B F 6 C

Consider the following:

Activity Normal time Predecessor
A 4 ---
B 2 ---
C 3 ---
D 1 A
E 4 B
F 6 C
G 2 D,E

If the duration of activity F is reduced by 1 days, the duration of the project can be reduced by _____ days. (Fill a number in the blank.)

Your Answer:

The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the crash time of all activities are zero:

Activity

Duration (days)

Immediate predecessor

Crash cost per period

A

2

-

$100

B

3

-

$150

C

11

-

$200

D

5

A

$30

E

7

B

$400

What is the cost for crashing the project by 1 day?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!