Question: Consider the following activity on arc project description with associated cost data shown in below table. The cost data represents the total cost and should
Consider the following activity on arc project description with associated cost data shown in below table. The cost data represents the total cost and should be considered linear with time
| Activity | Immediate Predecessor | Normal Duration (days) | Normal Cost ($) | Crash Duration (days) | Crash Cost ($) |
| A | --- | 5 | 100 | 3 | 180 |
| B | --- | 5 | 80 | 3 | 120 |
| C | --- | 5 | 100 | 5 | 100 |
| D | A, B | 4 | 100 | 2 | 200 |
| E | B | 3 | 75 | 3 | 75 |
| F | C | 8 | 200 | 6 | 220 |
| G | D, E | 6 | 100 | 5 | 180 |
Reduce the project duration to minimum duration and calculate the cost.