Question: Consider the following Activity-On-Node (AON) project (activity completion times are in days). Refer to the figure. How long will take to complete the project? A.

 Consider the following Activity-On-Node (AON) project (activity completion times are indays). Refer to the figure. How long will take to complete the

Consider the following Activity-On-Node (AON) project (activity completion times are in days). Refer to the figure. How long will take to complete the project? A. 11 days B. 13 days C. 12 days D. 14 days E. 15 days Consider the following Activity-On-Node (AON) project (activity completion times are in days). Refer to the figure. What is the critical path? A. none of the above B. ACDF C. ABEF D. ABDF E. ACEF