Question: Consider the following Activity-On-Node (AON) project (activity completion times are in days). Refer to the figure. Suppose that additional resources are provided to crash the


Consider the following Activity-On-Node (AON) project (activity completion times are in days). Refer to the figure. Suppose that additional resources are provided to crash the project completion time below its expected normal completion time. Which activities would be potential candidates for crashing? A. F B. B C. D D. A and B E. A and D Consider the following Activity-On-Node (AON) project (activity completion times are in days). Refer to the figure. What is the earliest start time (EST) and earliest finish time (EFT) of activity E? A. EST=8,EFT=10 B. EST=7,EFT=10 C. EST=10,EFT=7 D. EST=11,EFT=8 E. EST=8,EFT=11