Question: Consider the following AoN network and the table including associated activity times with their respective probabilities. Find the exact probability that the path S-A-B-T will

Consider the following AoN network and the table

Consider the following AoN network and the table including associated activity times with their respective probabilities. Find the exact probability that the path S-A-B-T will be the critical path. B S T D Activity A B Time (Days) Probability 8 1 10 0.6 15 0.4 6 0.3 10 0.7 9 1 D