Question: Consider the following batch flow process consisting of three process steps performed by three machines. Step 1 Step 2 Step 3 Processing time 2 mins/unit
Consider the following batch flow process consisting of three process steps performed by three machines.
| Step 1 | Step 2 | Step 3 | |
| Processing time | 2 mins/unit | 3 mins/unit | 1.5 mins/unit |
| Setup Time | 20 mins | No setup | No setup |
- Assume that the batch size is 10 parts. What is the capacity of the process?
- For a batch size of 50 parts, which step is the bottleneck for the process?
- What is the ideal batch size (i.e. one that minimizes inventory without affecting process capacity)?