Question: Consider the following breakdown : Optimistic time 3 1 weeks most likely - 4 0 weeks pessimistic - 4 3 weeks What is the estimated

Consider the following breakdown :
Optimistic time 31 weeks
most likely -40 weeks
pessimistic -43 weeks
What is the estimated expected (mean) time for the activity
a.31 weeks
b.38 weeks
c.39 weeks
d.40 weeks
e.43 weeks