Question: Consider the following case - study and then answer the following questions: you are a scrum master on a project: There are 8 0 user
Consider the following casestudy and then answer the following questions: you are a scrum master on a project:
There are user stories so far that the product owner listed in the backlog. The total estimate of the entire backlog in function points
The development team finished sprints. Here is the plan vs dont
Sprint
User stories
Planed FP
Completed FP
FP
FP
FP
FP
FP
FP
FP
FP
FP
FP
Answer the following questions:
Is the overall planning by the development team reasonable? Whywhy not?
As a scrum master, what would you do on sprint
How many function points should the development team plan for spring
Construct the sprint Burndown chart
What the development team progress so far after completing sprint How many sprints would you estimate to complete the project?
If we have software engineers working full time on this project, each getting paid k a month, what is the estimated development cost for the project?
If the product owner want to add more stories worth FP would we allow that? If not, explain, if yes, how many sprints you estimate to complete the project
In the middle of sprint suppose that the CEO came to you as the scrum master of the project and ask you to add story to this current sprint because it is extremely important, what would you do
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock