Question: Consider the following case - study and then answer the following questions: you are a scrum master on a project: There are 8 0 user

Consider the following case-study and then answer the following questions: you are a scrum master on a project:
There are 80 user stories so far that the product owner listed in the backlog. The total estimate of the entire backlog in 1000 function points
The development team finished 5 sprints. Here is the plan vs dont
Sprint
User stories
Planed FP
Completed FP
1
1-7
120 FP
110 FP
2
7,17
110 FP
150 FP
3
19-25
130 FP
20 FP
4
20-25
130 FP
135 FP
5
25-38
190 FP
120 FP
Answer the following questions:
Is the overall planning by the development team reasonable? Why/why not?
As a scrum master, what would you do on sprint 3?
How many function points should the development team plan for spring 6?
Construct the sprint Burndown chart
What the development team progress so far after completing sprint 5? How many sprints would you estimate to complete the project?
If we have 4 software engineers working full time on this project, each getting paid 100k a month, what is the estimated development cost for the project?
If the product owner want to add 10 more stories (worth 200 FP), would we allow that? If not, explain, if yes, how many sprints (you estimate) to complete the project
In the middle of sprint 5, suppose that the CEO came to you (as the scrum master of the project) and ask you to add story 29 to this current sprint because it is extremely important, what would you do?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!