Question: Consider the following cash flows for two mutually exclusive projects (A and B). a. Calculate NPV for both projects using discount rates of 12% and
Consider the following cash flows for two mutually exclusive projects (A and B).
a. Calculate NPV for both projects using discount rates of 12% and 17%.
b. What is the IRR of each project?
c. Which project would you choose to do if your discount rate was 12%? 17%? Explain how you made your decision.
Year A B
0 -31,000 -27,500
1 21,000 19,000
2 12,500 12,250
3 6,000 5,000
4 1,500 0