Question: Consider the following data and adopt chase production plan: - production rate = 15 - starting workers = 70 Month 1 Demand 600 Month 2
Consider the following data and adopt chase production plan:
- production rate = 15
- starting workers = 70
Month 1 Demand 600
Month 2 Demand 500
1. How many workers should you hire in the first month?
2. How many workers should you fire in the first month?
3. How many workers should you hire in the second month?
4. How many workers should you fire in the second month?
(for #5) Consider the following data and adopt Level production plan:
- production rate = 15
- starting workers = 70
Month 1 Demand 600
Month 2 Demand 500
5. How many workers should work in the plant for both the first and second months?