Question: Consider the following data for a project: table [ [ Activity , table [ [ Activity Time ] , [ ( days )

Consider the following data for a project:
\table[[Activity,\table[[Activity Time],[(days)]],\table[[Immediate],[Predecessor(s)]]],[A,2,-],[B,A,A],[C,5,A],[D,2,B],[E,1,B],[F,8,B, C],[G,3,D, E],[H,8,F],[I,4,F],[J,7,G, H, I]]
a. Draw the AON network diagram (with ES, EF, LS, LF, and Slack time)
b. Identify all paths in this project and their durations
c. Determine the project's critical path and duration
SHOW ALL WORK
 Consider the following data for a project: \table[[Activity,\table[[Activity Time],[(days)]],\table[[Immediate],[Predecessor(s)]]],[A,2,-],[B,A,A],[C,5,A],[D,2,B],[E,1,B],[F,8,B, C],[G,3,D, E],[H,8,F],[I,4,F],[J,7,G,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!