Consider the following data for a project to install a new server at the Northland Pines High School:
a. Choose the correct network diagram below.
A.
B.
c.
D.
b. Calculate the critical path for this project.
The critical path is A-C-F-H-J and the project duration is 24 days. (Enter your response as a whole number.)
c. How much slack is in each of the activities G,H, and I?