Question: Consider the following four projects with expected net present value (NPV) and standard deviation of NPV as follows: Project Expected NPV Standard deviation of NPV
Consider the following four projects with expected net present value (NPV) and standard deviation of NPV as follows:
| Project | Expected NPV | Standard deviation of NPV |
| A | R25 000 | 4 000 |
| B | R65 000 | 9 000 |
| C | R50 000 | 8 000 |
| D | R32 000 | 5 800 |
Which project would be regarded as the riskiest and which would be regarded as the least risky?
- A.
Project B is the most risky and project A is the least risky.
- B.
Project B is the most risky and project D is the least risky.
- C.
Project D is the most risky and project B is the least risky.
- D.
Project D is the most risky and project A is the least risky.
- E.
Project A is the most risky and project B is the least risky.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
