Question: Consider the following four--step assembly operation with quality problems. -The first resource has a processing time of 5 minutes per unit and one employee doing
Consider the following four--step assembly operation with quality problems.
-The first resource has a processing time of 5 minutes per unit and one employee doing the operation
The second resource has a processing time of 4 minutes per unit. It also has one employee doing the operation. However, this is a very delicate task and 0.83 of all products have to be scrapped after this step.
Two workers are staffed for the third resource. No quality problems occur at this resource and the processing time is 23 minutes per unit.
At the fourth and final resource, one operator handles the product. No quality problems exist at this step and the processing time is 12 minutes per unit.
What is the process capacity per hour? (keep two decimal)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts