Question: Consider the following information: Demand rate ( D ) 3 1 0 units per hour Lead time ( T ) 5 hours Container capacity (
Consider the following information:
Demand rate D units per hour
Lead timeT hours
Container capacity C units
Safety factor x
Part
a The number of kanban production cards is
enter your response here. Enter your response rounded up to the next whole number.
Part
b The cards will represent
enter your response here hours worth of demand. Enter your response rounded to one decimal place.
Part
c Suppose the lead time is reduced to hours. The number of kanban production cards is
enter your response here. Enter your response rounded up to the next whole number.
Part
The cards will represent
enter your response here hours worth of demand. Enter your response rounded to one decimal place.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock