Question: Consider the following information regarding a project: table [ [ Activity , Immediate,Duration ( days ) ] , [ A , Predecessor ( s

Consider the following information regarding a project:
\table[[Activity,Immediate,Duration (days)],[A,Predecessor(s),],[B,--,6],[C,A,4],[D,A,3],[E,B, C,3]]
If we consider the critical path, then: once this project is begun, what is the minimum time that will elapse (in days) before it is complete?
 Consider the following information regarding a project: \table[[Activity,Immediate,Duration (days)],[A,Predecessor(s),],[B,--,6],[C,A,4],[D,A,3],[E,B, C,3]] If