Question: Consider the following information. WEEK PART X 1 2 3 4 5 Gross Requirements 40 0 80 160 0 Scheduled Receipts 70 Projected On-Hand Inventory

Consider the following information.

WEEK
PART X 1 2 3 4 5
Gross Requirements 40 0 80 160 0
Scheduled Receipts 70
Projected On-Hand Inventory 130
Q = 50, LT = 3 weeks, Safety Stock = 5

Compute the planned order releases and projected on-hand inventory for component part X. Round your answers to the nearest whole number. If your answer is zero, enter "0".

WEEK
PART X 1 2 3 4 5
Gross Requirements 40 0 80 160 0
Scheduled Receipts 70
Projected On-Hand Inventory 130
Planned Order Releases 0 0 0