Question: / / / / / Consider the following line balancing problem, allowing a Takt Time of 5 minutes. Work Task Task Time (seconds) Task Predecessor(s)

/ / / / / Consider the following line balancing
/ / / / / Consider the following line balancing
/ / / / / Consider the following line balancing problem, allowing a Takt Time of 5 minutes. Work Task Task Time (seconds) Task Predecessor(s) A 70 . B 60 A 120 B ID E CD F 100 190 240 E, F Calculate the theoretical minimum number of workstations. ( task time/Takt Time) OA. 3 OB.2 OC..34 D.168 Consider the previous line balancing problem, allowing a takt time of 5 minutes. What jobs could be assigned at workstation 1 O A,B and C OB,C & G A,B,C&D A,D & E