Question: Consider the following linear programming mode: Maximize Profits = $6X + $5Y Subject to 3X + 2Y

Consider the following linear programming mode:

Maximize Profits = $6X + $5Y

Subject to

3X + 2Y <= 24 (hours of fabrication time)

2X + 4Y <= 40 (hours of assembly time)

X, Y >= 0

What are the optimal solution values of the decision variables, and how much slack does each constraint have, and what do these values mean?