Question: Consider the following network for a small MIS project along with the indicated resources required to complete the project: Available Resources: ET Technicians (1) available
Consider the following network for a small MIS project along with the indicated resources required to complete the project:
Available Resources:
ET Technicians (1) available @ $95/hr
Computer Tech (2) available @ $150
Computer Programmer (2) available @ $210
| ACTIVITY | INITIAL NODE | FINAL NODE | ACTIVITY DURATION (Days) | RESOURCES FOR EACH ACTIVITY |
| A | 1 | 2 | 2 | ET Technician |
| B | 1 | 3 | 3 | ET Technician |
| C | 1 | 4 | 3 | ET Technician |
| D | 2 | 5 | 3 | Computer Programmer |
| E | 2 | 9 | 3 | Computer Tech |
| F | 3 | 5 | 1 | Computer Programmer |
| G | 3 | 6 | 2 | Computer Tech |
| H | 3 | 7 | 3 | Computer Programmer |
| I | 4 | 7 | 5 | ET Technician |
| J | 4 | 8 | 3 | Computer Tech |
| K | 5 | 6 | 3 | Computer Tech |
| L | 6 | 9 | 4 | ET Technician |
| M | 7 | 9 | 4 | ET Technician |
| N | 8 | 9 | 3 | ET Technician |
| O | 9 | 10 | 2 | ET Technician |
The project is scheduled to begin on October 1, 2018. The working schedule is 8 hours per day and 5 days a week (40 hour work week). Assume any activity entering the starting point of another activity is an immediate predecessor. Answer the following questions using Microsoft Project or Primevara SureTrak:
- Show a Gantt chart for this project
- Identify the critical path and project completion time
- What is the total cost of this project (assume there are no materials and only labor)?
- Are there any problems that prevent this project from being completed by October 21, 2018? Explain?
- What is the earliest time the project can be completed without any conflicts?