Question: Consider the following network representation of a project. The notation used denotes the activity number and the time for each activity. For example, activity 1

Consider the following network representation of

Consider the following network representation of a project. The notation used denotes the activity number and the time for each activity. For example, activity 1 takes 4 units of time. 3(4) 46) 6(3) 5(2) 209) (a) Calculate the earliest completion time for each activity [15] (b)Calculate the latest completion time for each activity [15] (c) Calculate the slack for each activity [5] (d) Identify the critical path [5]