Question: Consider the following partial MPS record. Beginning inventory is 40 units. The firm uses a fixed order quantity of 70 units. What is the projected
Consider the following partial MPS record. Beginning inventory is 40 units. The firm uses a fixed order quantity of 70 units. What is the projected available amount in period 2?
Period: 1 2 3 4 5
Forecast: 50 5 40 25 50
Projected Available:
MPS:
Select one:
a.
15
b.
70
c.
50
d.
55
e.
125
The Master Production Schedule is often stated in..?
Select one:
a.
dollars
b.
material requirements
c.
rubles
d.
product specifications
e.
labor
What is the portion of the MPS called that lies between the current time and the demand time fence?
Select one:
a.
frozen
b.
gaseous
c.
slushy
d.
mucky
e.
liquid