Question: Consider the following portion of a project: Activities E & F are followers for Activity D. Activity D is 3 days, E is 1 day,
Consider the following portion of a project: Activities E & F are followers for Activity D. Activity D is 3 days, E is 1 day, F is 2 days. Assume that the late finish for both E & F is 8. What is the latest finish time for D?
| 3 | ||
| 8 | ||
| cannot determine from the information given | ||
| 6 | ||
| 7 |