Question: Consider the following portion of a project: Activities E & F are followers for Activity D. Activity D is 3 days, E is 1 day,

Consider the following portion of a project: Activities E & F are followers for Activity D. Activity D is 3 days, E is 1 day, F is 2 days. Assume that the late finish for both E & F is 8. What is the latest finish time for D?

3

8

cannot determine from the information given

6

7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!