Question: Consider the following problem with 5 activities A1, A2, A3, A4, A5. Activity A1 can be started immediately and take 2 days to complete. Activity
Consider the following problem with 5 activities A1, A2, A3, A4, A5. Activity A1 can be started immediately and take 2 days to complete. Activity A2 depends on A1, and takes 2 days to complete. Activi