Question: Consider the following process model The data associated with this model are: Activity Cycle Time Processing Time Cost Check stock availability 15 minutes 10 minutes
Consider the following process model

The data associated with this model are:
| Activity | Cycle Time | Processing Time | Cost |
| Check stock availability | 15 minutes | 10 minutes | $5 |
| Confirm order | 30 minutes | 3 minutes | $0 |
| Reject order | 60 minutes | 4 minutes | $0 |
| Ship goods | 3 hours | 30 minutes | $10 |
| Emit invoice | 1 hour | 15 minutes | $0 |
| Archive order | 1 hour | 10 minutes | $0 |
Assume that items are in stock 75% of the time. There is one ERP system, 3 warehouse staff, and 2 sales staff. All work eight hour days, five days a week (assume ERP system only operational during work hours). The cost to run the ERP system is $10/hour. The wages for warehouse staff are $25/hour, and the wages for sales staff are $30/hour.
- Calculate the cycle time for this process
- Calculate the cycle time efficiency for this process
- Calculate the expected cost of the process
- Calculate the pooled unit load for each resource
- Calculate the theoretical capacity for each resource
- Identify the bottleneck resource
- How many orders can this process handle in one work week?
- Assume that in a given day 30 orders arrive. What is the utilization rate for each resource?