Consider the following process: Resource Processing Time (Min./Unit) Number of workers 1 10 2 2 6 1
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider the following process:
Resource | Processing Time (Min./Unit) | Number of workers |
1 | 10 | 2 |
2 | 6 | 1 |
3 | 16 | 3 |
A. What is the bottleneck?
B. The process capacity is _______ units per hour [please use numerals to fill in the blank]
C. If demand is twelve units per hour, the utilization of each resource is ?
If demand is twelve units per hour, the implied utilization of each resource is ?
Related Book For
Operations Management Sustainability And Supply Chain Management
ISBN: 9780137476442
14th Edition
Authors: Jay Heizer, Barry Render, Chuck Munson
Posted Date: