Question: Consider the following process. The processing time ( sec / unit ) is given for each worker. M 1 4 0 sec M 2 1

Consider the following process. The processing time (sec/unit) is given for each worker.
M1
40 sec
M2
120 sec
M3
140 sec
a) Calculate the following design parameters for this process:
Designed CT for Stage 1
sec / unit
Designed CT for Stage 2
sec / unit
Bottleneck
Stage:
Process Designed CT
sec / unit
Process Capacity
units