Question: Consider the following Program Evaluation Review Technique (PERT) network. 5 15 E 13 7 6 11 F H 10 10 The activities and their respective

Consider the following Program Evaluation Review

Consider the following Program Evaluation Review Technique (PERT) network. 5 15 E 13 7 6 11 F H 10 10 The activities and their respective durations are given in the following table. Activity Duration (days) A 5 B 7 15 D 10 E 13 F 19 G 16 H 10 11 Which of the following paths of the given network is the critical path? a. A C F H I b.BDG I C. BDF H I d. E F H