Question: Consider the following project activities: a . ( * ) Draw the project network diagram. b . ( * ) Identify all the paths through

Consider the following project activities:
a.(*) Draw the project network diagram.
b.(*) Identify all the paths through the network and their
lengths.
c.(*) Identify all the critical activities and path(s). How
long will the entire project take?
d.(**) After you complete part b and before you perform
the forward and backward passes, you should already
be able to tell that activities A and N are on the critical
path(s). Why?
e.(**) After constructing the project network diagram,
management comes up with the following informa-
tion regarding how many days certain activities can be
crashed and at what cost:
Suppose that every day the project goes on costs the com-
pany $3,500. How many days should management crash
the project? What activities should it crash? What is the
new project length? Consider the following project activities:Imtin
This HY
a.(*) Draw the project network diagram.
b.(*) Identify all the paths through the network and their
lengths.
c.(*) Identify all the critical activities and path(s). How
long will the entire project take?
d.(**) After you complete part b and before you perform
the forward and backward passes, you should already
be able to tell that activities A and N are on the critical
path(s). Why?
e.(**) After constructing the project network diagram,
management comes up with the following informa-
tion regarding how many days certain activities can be
crashed and at what cost:
Suppose that every day the project goes on costs the com-
pany $3,500. How many days should management crash
the project? What activities should it crash? What is the
new project length?
 Consider the following project activities: a.(*) Draw the project network diagram.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!