Question: Consider the following project activities: Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early

Consider the following project activities:

Consider the following project activities: Draw

  1. Draw an Activity on Node (AON) diagram to reflect the flow of these activities.
  2. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity.
  3. Calculate the slack for each activity.
  4. Identify all activities on the Critical Path.
  5. What happens if activity B is delayed by 4 months? How does that change your answers to questions b, c, and d?
Duration Activity Predecessor (months) A 5 B A 6 C A 3.5 D A 4.5 E C D 6 F B, E 5 G F 3.5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!