Question: Consider the following project: Activity Immeadlate Predecessors Durations (weeks) 3 A B A 3 C 2 D B 3 E 7 F 3 G D.

Consider the following project: Activity

Consider the following project: Activity Immeadlate Predecessors Durations (weeks) 3 A B A 3 C 2 D B 3 E 7 F 3 G D. E 6 C 2 Which activity is not a critical activity? G B