Question: Consider the following project: Activity Immediate Predecessor Duration in Weeks A None 2 B None 3 C A 4 D A and B 4 E
Consider the following project:
Activity Immediate Predecessor Duration in Weeks
A None
B None
C A
D A and B
E C and D
What is the total time to complete the project?
a weeks
b weeks
c weeks
d weeks
e None of the above