Question: Consider the following project: Activity Predecessor Time ( Days ) A - 4 B - 5 C A 8 D B 3 E C ,

Consider the following project:
Activity Predecessor Time (Days)
A -4
B -5
C A 8
D B 3
E C,D 3
What is the critical path duration?
Group of answer choices
26 days
23 days
15 days
Need more information to calculate
11 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image