Question: Consider the following project. Activity Predecessor(s) Duration (days) A -- 6.3 B A 2.2 C A 2.4 D C 4.2 E C 2.9 F B

Consider the following project.

Activity Predecessor(s) Duration (days)
A -- 6.3
B A 2.2
C A 2.4
D C 4.2
E C 2.9
F B 3.4
G D, F 4.0
H D, E 3.2
I G, H 2.6

What would be the effect of delaying activity E by 1.5 days?

A.

Delaying activity E by 1.5 days will have no effect on the project duration.

B.

Delaying activity E by 1.5 days will delay the entire project by 1.5 day.

C.

Delaying activity E by 1.5 days will shorten the entire project by 0.6 day.

D.

Delaying activity E by 1.5 days will delay the entire project by 0.6 day.