Question: Consider the following project. Activity Predecessor(s) Duration (days) A -- 6.3 B A 2.2 C A 2.4 D C 4.2 E C 2.9 F B
Consider the following project.
| Activity | Predecessor(s) | Duration (days) |
|---|---|---|
| A | -- | 6.3 |
| B | A | 2.2 |
| C | A | 2.4 |
| D | C | 4.2 |
| E | C | 2.9 |
| F | B | 3.4 |
| G | D, F | 4.0 |
| H | D, E | 3.2 |
| I | G, H | 2.6 |
What would be the effect of delaying activity E by 1.5 days?
| A. | Delaying activity E by 1.5 days will have no effect on the project duration. | |
| B. | Delaying activity E by 1.5 days will delay the entire project by 1.5 day. | |
| C. | Delaying activity E by 1.5 days will shorten the entire project by 0.6 day. | |
| D. | Delaying activity E by 1.5 days will delay the entire project by 0.6 day. |