Question: Consider the following project: Activity Time Predecessor A 1 2 - B 1 0 - C 9 A D 1 5 A E 7 B

Consider the following project:
Activity Time Predecessor
A
1
2
-
B
1
0
-
C
9
A
D
1
5
A
E
7
B
F
8
D
,
E
G
1
3
C
,
F
Which activity has a slack time that is different from all others