Question: Consider the following project: Activity Time Predecessor A 12 - B 10 - C 9 A D 15 A E 7 B F 8 D,
Consider the following project: Activity Time Predecessor A 12 - B 10 - C 9 A D 15 A E 7 B F 8 D, E G 13 C, F
What is the fastest this project can be completed