Question: Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and the early and late start and end

Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and the early and late start and end times and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and that no task can be crashed to less than half its original duration, you would like to minimize the total of number of tasks crashed, and tasks A and N cannot be crashed at all? (20 points)

Task

Predecessors

Most Likely Duration

A

-

3

B

A

12

C

A

7

D

A

6

E

B

10

F

E

7

G

C

18

H

C

13

I

G

10

J

H

13

K

D

10

L

K

11

M

L

7

N

F, I, J, M

2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!