Question: Consider the following project for which you have been given the following data. begin{tabular}{|c|c|c|c|c|} hline Task & Duration (Weeks) & Optimistic & Most Likely &

 Consider the following project for which you have been given the

Consider the following project for which you have been given the following data. \begin{tabular}{|c|c|c|c|c|} \hline Task & Duration (Weeks) & Optimistic & Most Likely & Pessimistic \\ \hline A & 12 & 9 & 11 & 12 \\ \hline B & 9 & 7 & 8 & 9 \\ \hline C & 10 & 8 & 9 & 10 \\ \hline D & 10 & 7 & 9 & 10 \\ \hline E & 24 & 21 & 23 & 24 \\ \hline F & 10 & 7 & 8 & 10 \\ \hline G & 35 & 30 & 33 & 35 \\ \hline H & 40 & 37 & 39 & 40 \\ \hline I & 15 & 13 & 14 & 15 \\ \hline J & 4 & 2 & 3 & 4 \\ \hline K & 6 & 4 & 5 & 6 \\ \hline \end{tabular} There are five paths in this project: \begin{tabular}{|c|c|} \hline Path & Duration (Weeks) \\ \hline A-I-K & 33 \\ \hline A-F-K & 28 \\ \hline A-C-G-J-K & 67 \\ \hline B-D-H-J-K & 69 \\ \hline B-E-J-K & 43 \\ \hline \end{tabular} Assume that you are dealng with an "uncrashed" project. What is the "Expected Completion Date" for this project (PERT). What is the standard deviation for the "expected completion date" for this project? What is the probability that completion will take 4 weeks more than the "expected completion date"? Consider the following project for which you have been given the following data. \begin{tabular}{|c|c|c|c|c|} \hline Task & Duration (Weeks) & Optimistic & Most Likely & Pessimistic \\ \hline A & 12 & 9 & 11 & 12 \\ \hline B & 9 & 7 & 8 & 9 \\ \hline C & 10 & 8 & 9 & 10 \\ \hline D & 10 & 7 & 9 & 10 \\ \hline E & 24 & 21 & 23 & 24 \\ \hline F & 10 & 7 & 8 & 10 \\ \hline G & 35 & 30 & 33 & 35 \\ \hline H & 40 & 37 & 39 & 40 \\ \hline I & 15 & 13 & 14 & 15 \\ \hline J & 4 & 2 & 3 & 4 \\ \hline K & 6 & 4 & 5 & 6 \\ \hline \end{tabular} There are five paths in this project: \begin{tabular}{|c|c|} \hline Path & Duration (Weeks) \\ \hline A-I-K & 33 \\ \hline A-F-K & 28 \\ \hline A-C-G-J-K & 67 \\ \hline B-D-H-J-K & 69 \\ \hline B-E-J-K & 43 \\ \hline \end{tabular} Assume that you are dealng with an "uncrashed" project. What is the "Expected Completion Date" for this project (PERT). What is the standard deviation for the "expected completion date" for this project? What is the probability that completion will take 4 weeks more than the "expected completion date

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!