Question: Consider the following project. If the project extends beyond 42 days, a lumpsum penalty of $25000 needs to be paid. What is the expected penalty?

Consider the following project. If the project extends beyond 42 days, a lumpsum penalty of $25000 needs to be paid. What is the expected penalty? Round to 2 decimals for all calculations. Paths A-B-C- D Expected Path Variances duration E-F-G-H I-J-K-L Answer: 6,4 4.9 2.5 43 34 30
 Consider the following project. If the project extends beyond 42 days,

Consider the following project. If the project extends beyond 42 days, a lumpsum penalty of $25000 needs to be paid. What is the expected penalty? Round to 2 decimals for all calculations