Question: Consider the following project. If the project extends beyond 42 days, a lumpsum penalty of $25000 needs to be paid. What is the expected penalty?
Consider the following project. If the project extends beyond 42 days, a lumpsum penalty of $25000 needs to be paid. What is the expected penalty? Round to 2 decimals for all calculations. Paths A-B-C- D Expected Path Variances duration E-F-G-H I-J-K-L Answer: 6,4 4.9 2.5 43 34 30
Consider the following project. If the project extends beyond 42 days, a lumpsum penalty of $25000 needs to be paid. What is the expected penalty? Round to 2 decimals for all calculations
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
